File #: 25-2753    Version: 1 Name:
Type: Discussion Items Status: Agenda Ready
File created: 3/26/2025 In control: County Council
On agenda: 4/1/2025 Final action:
Title: Budget Adjustment: The Salt Palace Requests to Transfer $147,000 in Under-Expend Budget from the Concourse Carpet Project to the Ballroom Lighting Replacement Project
Attachments: 1. Staff Report, 2. 34504 - Adjustment to Ballroom Light Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Requested Agenda Date:

4/1/2025

 

Requested Agenda Title:

Budget Adjustment: The Salt Palace Requests to Transfer $147,000 in Under-Expend Budget from the Concourse Carpet Project to the Ballroom Lighting Replacement Project

 

Requested Agenda Item Description: Additional funding is needed for the ballroom lighting capital project. This project is to update the lighting in the Salt Palace ballroom to LED fixtures. When the bids were received, they came in over the projected budget and an additional $147,000 is needed to complete the project. The funding is requested to be transferred from the completed concourse carpet replacement project which has sufficient underexpend to cover the increase.


Requested Action: Discussion - Vote Needed

 

Presenter(s) (with titles): Hoa Nguyen, Council Budget and Policy Analyst  

 

Time Needed: Less than 5 MINS

 

Is this Item Time-Sensitive and/or Requesting a Time-Certain? No

 

Requesting Staff Member: Dan Hayes, General Manager, ASM Global - Salt Lake

 

Are Supporting Documents Needed for this Agenda Item Request? Yes